• 100th Street Bridge Update

    This upcoming weekend will be the demolition of the old bridge.  The sequence of events are as follows:
     
    Friday morning 3/27/20 at 9 AM until 6PM:  US-131 NB and SB will have single left lane closures for guard rail and cable rail removals.
     
    Friday evening 3/27/20 at 6PM:  US-131 NB and SB will continue to have the left lane closed with the right lane going up and over 100th Street so that no traffic goes under the structure as we remove it.  For the safety of US-131 traffic and 100th Street traffic turns onto and off of 100th Street will not be allowed.  Please follow the detours to the 84th street interchange.  This will be in place until Monday night at 6PM.  This is for the bridge demolition and to set up the traffic shift.
     
    Monday evening 3/30/20 at 6PM:  All ramps will be open.  Access to and from 100th street to the ramps will be open.  US-131 NB and SB will have 2 lanes open but will be shifted to the outside for the bridge pier removal in the median.